Applied Digital Delta Forge 1 AI campus (about 300 acres near Boyce)
proposed Boyce area, Rapides Parish, Louisiana
DeveloperApplied Digital
UtilityCleco
Capacity300 MW
Investment$3.6bn
Latest
2026-05-26
State economic developers and Cleco announced the $3.6B campus; Cleco's service package for it still needs Louisiana PSC approval
Notes: 300 MW is the critical IT load of the first two buildings; the utility-side load is larger. Applied Digital is to pay for the grid infrastructure. Operations are targeted for mid-2027.
Sources: Louisiana Economic Development · Cleco · EEI