Applied Digital Delta Forge 1 AI campus (about 300 acres near Boyce)

proposed Boyce area, Rapides Parish, Louisiana

DeveloperApplied Digital
UtilityCleco
Capacity300 MW
Investment$3.6bn

Latest

2026-05-26

State economic developers and Cleco announced the $3.6B campus; Cleco's service package for it still needs Louisiana PSC approval

Notes: 300 MW is the critical IT load of the first two buildings; the utility-side load is larger. Applied Digital is to pay for the grid infrastructure. Operations are targeted for mid-2027.

Sources: Louisiana Economic Development · Cleco · EEI