Applied Digital campus near Toronto (430 MW)

withdrawn Toronto, Deuel County, South Dakota

DeveloperApplied Digital
UtilityOtter Tail Power
Capacity430 MW
Investment$5bn

Latest

2026-03-16

Applied Digital said the campus is unlikely to go forward and it will let its land agreement lapse after lawmakers rejected data center tax incentives

Notes: Still on EEI's October 2026 list of utility-announced projects; the developer's own statements say it is off. The company said it may come back if incentives or power conditions change.

Sources: South Dakota Searchlight · DCD · Dakota News Network