Project Eagle / Project Baccara data center (160 acres near Luke AFB)
approved Glendale, Maricopa County, Arizona
Developerunknown (Project Eagle / Project Baccara)
Utilityon-site natural gas generators (about 700 MW, per the City of Surprise)
Capacityunknown
Investment$36bn
Latest
2026-10-28
Glendale City Council approved annexing and rezoning the site at Litchfield Road and Olive Avenue, about 2 miles from Luke Air Force Base's front gate
Notes: Reported value $36 billion for two data center buildings. Maricopa County supervisors approved a military compatibility permit in May over one no vote, after residents raised groundwater and air quality concerns. Construction is set to start in November, with the first building opening in 2028.
Sources: Arizona's Family