2026-10-29
Protesters from Roanoke to Richmond called for a moratorium as grading continues; county administrators and supervisors declined interviews
Notes: Three data center buildings planned; the first is due in 2028 and will be air-cooled. Google paid $14.06M for the land (a discounted $45,000 an acre) plus a $4M grant to the county, and gets a personal property tax grant and expedited permits. Data centers were added to the park's zoning in November 2024 at a hearing with no opposition. Grading began in September under a county land disturbance permit while state wetland permits are pending.
Sources: Botetourt County · WSET · Cardinal News · Virginia DEQ