Port of Little Rock data center (five buildings, 1.43 million sq ft)
proposed Little Rock, Pulaski County, Arkansas
DeveloperGoogle
Utilityunknown
Capacityunknown
Investment$1bn
Latest
2026-10-20
City directors deadlocked 4-4, with one recusal, on a six-month pause on large data center approvals, so it failed; an 18-month version also failed in August
Notes: Lead via The Data Center Debate. Google was named as the company behind the $1 billion plan in January. Google has held invitation-only meetings about the project. Six votes are needed to pass a moratorium in Little Rock.
Sources: KATV · Arkansas Democrat-Gazette