Microsoft Granger data center campus (about 900 acres)
proposed Granger, St. Joseph County, Indiana
DeveloperMicrosoft
Utilityunknown
Capacityunknown
Investmentunknown
Latest
2026-10-06
County Redevelopment Commission and commissioners approved a second MOU in which Microsoft pays about $53M for water and sewer to the site; not final project approval
Notes: Between Bittersweet and Currant roads with I-90 to the north. Six buildings and up to 300 jobs reported. Microsoft said building construction could start late fall 2026 or early 2027.