Project River industrial campus
proposed Charleston area, Bradley County, Tennessee
DeveloperWright family (Project River)
UtilityTVA (backup only)
Capacity1500 MW
Investment$11.3bn
Latest
2026-08-25
Annexation into Cleveland and rezoning were requested
Notes: About 850 acres west of I-75 with a planned 1,000 MW gas plant and 500 MW biomass plant. The developers say the power user will most likely be a data center ($7.3B of the total), but no customer is signed.
Sources: Times Free Press · WDEF