Projects › Virginia
Tuckahoe Technology Park (about 871 acres, up to 900 MW)
proposed Goochland (TOD West, near Route 288), Goochland County, Virginia
DeveloperTract (VALCO2 Goochland, LLC)
UtilityDominion Energy (engineering letter of authorization executed, per an SCC filing)
Capacity900 MW
Investmentunknown
Latest
2026-10-19
Several hundred Henrico and Goochland residents packed a community meeting on Tract's campus and three other proposed campuses in eastern Goochland; the formal conditional use permit application filed in August has not yet been scheduled for the Planning Commission
Notes: Application CU-2026-00014, seven development areas on 871 acres in the TOD West part of the county's technology overlay district, where data centers need a conditional use permit. The county and its EDA signed NDAs with Tract in 2023 and 2025 and released them in June. Opponents say the plan is a 12-building campus that would take five to seven years to build. A Henrico supervisor says Henrico must keep selling water to Goochland under contract until at least 2036.
Sources: Goochland County · Richmond BizSense · Henrico Citizen
What this means for you
This is one of the biggest projects we track: about 900 MW of power.
- Water: A Henrico supervisor says Henrico must keep selling water to Goochland under contract until at least 2036.
- Land: Several hundred Henrico and Goochland residents packed a community meeting on Tract's campus and three other proposed campuses in eastern Goochland; the formal conditional use permit application filed in August has not yet been scheduled for the Planning Commission Application CU-2026-00014, seven development areas on 871 acres in the TOD West part of the county's technology overlay district, where data centers need a conditional use permit.
Only what our sources say. Know more? Tell us.
Share this page
Send it to your neighbors, your local Facebook or Nextdoor group, or your county officials.