Memphis Light, Gas and Water (MLGW)

Data center projects in our tracker that name Memphis Light, Gas and Water (MLGW) as the utility or power supplier. The name is matched to the field exactly as our sources report it; see each project for details.

Projects2
States1
Known capacity300 MW
Blocked / withdrawn0

Projects

ProjectLocationStatusRoleLatest
xAI Colossus 2 (Tulane Rd, Memphis)
Listed as: MLGW / TVA + Southaven onsite gas
Shelby County, TNunder constructionUtility2026-03-10
MDEQ issued permit for 41 turbines (1.2 GW) at Southaven power plant serving Colossus 2; SELC appealed
xAI Colossus 1 (Memphis)
Listed as: MLGW / TVA + onsite gas turbines
Shelby County, TNoperatingUtility2026-01-15
EPA rule (Jan 2026) said even temporary turbines need permits; groups challenging the July 2025 Shelby County permit for 15 turbines

States

Tennessee

Sources: E&E News · SELC · Commercial Appeal

See an error, or a project we link to the wrong company? Request a correction.