Companies › SB Energy

SB Energy

Data center projects in our tracker that name SB Energy as a developer/owner. The name is matched to the field exactly as our sources report it; see each project for details.

Projects2
States2
Known capacity1,200 MW
Blocked / withdrawn0

Projects

ProjectLocationStatusRoleLatest
Stargate Milam County (SB Energy)
Listed as: SB Energy / OpenAI
Milam County, TXunder constructionDeveloper / partner2026-10
Phase 1 'Freebird' ($470M, 4 halls) under construction; operations expected 2027
PORTS-Pike Technology Campus
Listed as: SB Energy (SoftBank)
Pike County, OHunder constructionDeveloper / partner2026-10
OPSB local public hearing on the AEP Baku-Gavin 765 kV line (~51 miles, ~$1.1B, paid by the data center) set for Oct. 27 in Jackson; early…

States

Ohio · Texas

Sources

  1. https://milamdc.com/
  2. https://www.datacenterdynamics.com/en/news/openai-stargates-milam-texas-freebird-data-center-to-span-548950-sq-ft-in-first-phase/
  3. https://portscampus.com/updates/
  4. https://opsb.ohio.gov/cases/26-0426-el-btx
  5. https://www.aepohio.com/company/news/view?releaseID=11922
  6. https://www.enr.com/articles/63525-nvidia-partners-with-sb-energy-on-10-gw-ai-data-center-complex-in-ohio

See an error, or a project we link to the wrong company? Request a correction.