Companies › xAI
xAI
Data center projects in our tracker that name xAI as a developer/owner. The name is matched to the field exactly as our sources report it; see each project for details.
Projects3
States2
Known capacity300 MW
Blocked / withdrawn0
Projects
| Project | Location | Status | Role | Latest |
|---|---|---|---|---|
| xAI Colossus 2 turbines (Southaven, serving Memphis) Listed as: xAI (MZX Tech) | DeSoto County, MS | approved | Developer / partner | 2026-04-09 Residents, NAACP and groups appealed state air permit for 41 gas turbines |
| xAI Colossus 2 (Tulane Rd, Memphis) Listed as: xAI | Shelby County, TN | under construction | Developer / partner | 2026-03-10 MDEQ issued permit for 41 turbines (1.2 GW) at Southaven power plant serving Colossus 2; SELC appealed |
| xAI Colossus 1 (Memphis) Listed as: xAI | Shelby County, TN | operating | Developer / partner | 2026-01-15 EPA rule (Jan 2026) said even temporary turbines need permits; groups challenging the July 2025 Shelby County permit for 15 turbines |
States
Sources
- https://mississippitoday.org/2026/04/10/xai-southaven-permit-appeal/
- https://www.selc.org/press-release/groups-appeal-air-permit-for-xais-personal-power-plant-in-north-mississippi/
- https://www.eenews.net/articles/xai-gets-air-permit-for-unauthorized-gas-turbines/
- https://www.selc.org/news/inside-memphis-fight-against-xai/
- https://www.commercialappeal.com/story/money/business/development/2026/01/15/epa-updated-turbine-regulations-xai-impact-memphis-tn-southaven-ms/88200392007/
See an error, or a project we link to the wrong company? Request a correction.